FringeNYC 2007 :
JAN/ FEB - APPLICATIONS / INTERNS
January 15th - Early / International Application Deadline
February 14th - Final General / FringeAL FRESCO / FringeJR Application Deadline
MARCH - ADJUDICATION / VENUES
March 4th - Adjudicator Training Day / Applications picked up
March 12th - First NEWBIE meeting (Every OTHER Monday)
March 8th - Additional Adjudicator Training / Applications picked up
March 17th - ADJUDICATION DAY – One Person Shows
March 18th - ADJUDICATION DAY – One Person Shows
March 22nd - ADJUDICATION PANEL MEETING
March 24th - ADJUDICATION DAY – Smaller Categories
March 25th - ADJUDICATION DAY – Dance / Movement, Clown / Masque / Puppet + Vaudeville / Sideshow / Magic / Burlesque, Sketch / Improv / Stand-Up, Multi-Media + Other + Spoken Word / Poetry
March 24th or 25th - ADJUDICATION PANEL MEETING
March 31st - Most Venues confirmed
March 31st - ADJUDICATION DAY – Plays (turn clocks forward!)
  APRIL - NOTIFICATION/ SPECIAL PROGRAMS /SPONSORS
April 1st - ADJUDICATION DAY - Plays
April 5th - ADJUDICATION PANEL MEETING
April 7th - ADJUDICATION DAY – Musicals
April 8th - ADJUDICATION DAY – Musicals
April 12th - ADJUDICATION PANEL MEETING
April 14th - PANEL DAY – Final Meeting / Reporting
April 15th - PANEL DAY – Final Meeting / Reporting
April 16th – 18th - FINAL DECISIONS / EXEC COMMITTEE MEETS
April 17th - First FringeNYC Staff Meetings start
April 18th – 23rd - Notifications Mailed
  MAY - ASSIGNING TO VENUES
May 8th - List of accepted shows (Title / Locale) on website
May 15th - Deadline STEP ONE: tech, fee, agmt.
May 19th, 20th - Marketing Speed Dates
May 22nd - Follow up with delinquents
May 22nd - Drop Dead date for Participants
May 25th - Deadline STEP TWO: Marketing Information Form submitted online
May 29th - Show titles / blurbs / genres on www.FringeNYC.org
May 29th - Show titles / blurbs / genres into FringeNYC Slice-o-Matic
  JUNE - PROGRAMMING / PRESS BEGINS
June 3rd - TOWN MEETING
June 3rd - Deadline STEP THREE: Press Pkg / Image uploaded / PG Ad reserved
June 10th - Ads Due
June 10th - Drop Dead alternates deadline
June 11th - Community Ads Due (real deadline)
June 16th - Marketing Mixer
 

JULY - PUBLISHING / TICKETING
July 1st - Programming Complete
July 1st - Program Guide draft to printer
July 14th, 19th, 22nd - STEP FOUR: MANDATORY ACR B O Training Session
July 16th - Press draft of Program Guide Complete
July 20th - Program Guide hits street
July 20th - Phone / Web orders begin

  AUGUST - FESTIVAL / BOX OFFICE
Aug 3rd - FringeCENTRAL Opens
Aug 10th – 26th - FringeNYC 2007

Does not include organizational responsibilities (Board, Fundraising, Financial, Legal, etc.)